Join the Bayvista mailing list
Email:

NEW! Bayvista becomes a reality!
Animated progression of BayVista under-construction. Click here to watch.

 

Development progress for Bayvista

04- 25-07 - Bayvista  is completed. (See)
µClick here to see a virtual tour of the club house, pool, and views
µClick here to tour the decorated sales model

01- 11-06 - Bayvista
 is becoming a reality . (See)

01-11-05
Aerial photograph of construction site. (Photos)

10-15-05
Steel erection begins. (Photos)

08-08-05
Production pile was started and project date of completion Aug 20, 2005

08-05-05 Site trailer set on site.

07-06-05 We order 304, 20 foot, 12'" x 12'", concrete pilings.

07-05-05 Test Pile Program complete.

07-01-05 We received test piles result.

06-30-05 Drive Test Piles.

06-13-05 Order Test Piles (5).

03-11-05 Site Clearing.

03-01-05 First on-site production meeting with architect, engineer, contractor, and owner

01-17-05 Architectural Plans approved by City of Virginia Beach.

12-07-04 Final Site Plan approved.

12-02-04 Building permit approved.

11-01-04 Site Plan submitted for 3rd review.

10-04-04 Architectural plans submitted.

09-03-04 Site Plan submitted for 2nd review.

07-30-04 Site Plan submitted.

PROJECT PHOTOS: Construction Progress






Close-up view of steel erection to begin. 10-15-05


Aerial view of steel erection to begin. 10-15-05

Forms for Grade Beams 09-06-05

20 ft concrete piles ready to be installed 08-08-05

Water Front Marine is installing concrete piles 08-05-05

S.B. Ballard Superintendent Randy Parson is checking piles 08-05-05