Development progress for Bayvista
04- 25-07 - Bayvista is completed. (See)
µClick
here to see a virtual tour of the club house, pool, and views
µClick
here to tour the decorated sales model
01- 11-06 - Bayvista is becoming a reality
. (See)
01-11-05 Aerial photograph of construction site.
(Photos)
10-15-05 Steel erection begins.
(Photos)
08-08-05 Production pile was started and project
date of completion Aug 20, 2005
08-05-05 Site trailer set on site.
07-06-05 We order 304, 20 foot, 12'" x 12'",
concrete pilings.
07-05-05 Test Pile Program complete.
07-01-05 We received test piles result.
06-30-05 Drive Test Piles.
06-13-05 Order Test Piles (5).
03-11-05 Site Clearing.
03-01-05 First on-site production meeting with
architect, engineer, contractor, and owner
01-17-05 Architectural Plans approved by City
of Virginia Beach.
12-07-04 Final Site Plan approved.
12-02-04 Building permit approved.
11-01-04 Site Plan submitted for 3rd review.
10-04-04 Architectural plans submitted.
09-03-04 Site Plan submitted for 2nd review.
07-30-04 Site Plan submitted.
PROJECT PHOTOS:
Construction
Progress



Close-up view of steel erection to begin. 10-15-05

Aerial view of steel erection to begin. 10-15-05

Forms for Grade Beams 09-06-05

20 ft concrete piles ready to be installed 08-08-05

Water Front Marine is installing concrete piles
08-05-05

S.B. Ballard Superintendent Randy Parson is checking
piles 08-05-05
|